This is an attempt in putting a value in days worked on steel. Every step is made with propane and with no tools except the required ones. The large amount of steel is for avoiding rounding off errors as all calculations are done with full days of work.
+
{{InterwikiLink:ComparativeValueOfSteel}}
  
'''For 100000g [[steel]]'''
+
This is an attempt in putting a value in days worked on steel.  The large amount of steel is for avoiding rounding off errors as all calculations are done with full days of work.
 +
 
 +
'''Best case scenario for 100000g [[steel]]''' (Every step is made with best tools, drills and quarries.)
 +
 
 +
104 days
 +
 
 +
*54600g [[Iron]]
 +
*104 days
 +
**72800g [[Iron ore]]
 +
**70 days
 +
***104250g [[Hematite]]
 +
***28 days
 +
**14560g [[Propane]]
 +
**97 days
 +
***19400g [[gas]]
 +
***65 days
 +
****4014g wood
 +
****7 days
 +
**145600g [[Limestone]]
 +
**33 days
 +
*18200g [[Propane]]
 +
*122 days
 +
**24400g [[gas]]
 +
**82 days
 +
***6710 wood
 +
***12days
 +
*182000g [[Limestone]]
 +
*42 days
 +
 
 +
Sum --- 766 days;
 +
 
 +
One day of work is worth '''130.5 grams of steel'''.
 +
----
 +
'''Medium case for 100000g [[steel]]''' (Every step is made with no tools except the required ones.)
  
 
104 days
 
104 days
Line 15: Line 48:
 
***19400g [[gas]]
 
***19400g [[gas]]
 
***194 days
 
***194 days
 +
****4014g wood
 +
****14 days
 
**145600g [[Limestone]]
 
**145600g [[Limestone]]
 
**133 days
 
**133 days
Line 21: Line 56:
 
**24400g [[gas]]
 
**24400g [[gas]]
 
**244 days
 
**244 days
 +
***6710 wood
 +
***23days
 
*182000g [[Limestone]]
 
*182000g [[Limestone]]
 
*166 days
 
*166 days
  
Sum --- 1338 days;  
+
Sum --- 1375 days;  
 +
 
 +
One day of work is worth '''72.7 grams of steel'''.
 +
 
 +
 
  
One day of work is worth '''74.7 grams of steel'''.
 
  
 
Note: I realize this doesn't include time and cost for trasport, tools and machinery.
 
Note: I realize this doesn't include time and cost for trasport, tools and machinery.
 +
 +
[[Category: Game mechanics]]

Latest revision as of 01:09, 22 March 2014

Interwiki

българскиDeutschEnglishEspañolEsperantoFrançaisItalianoLietuviųLojbanNederlandsPolskaPortuguêsРусскийSuomiSvenskaTürkçe中文

This is an attempt in putting a value in days worked on steel. The large amount of steel is for avoiding rounding off errors as all calculations are done with full days of work.

Best case scenario for 100000g steel (Every step is made with best tools, drills and quarries.)

104 days

Sum --- 766 days;

One day of work is worth 130.5 grams of steel.


Medium case for 100000g steel (Every step is made with no tools except the required ones.)

104 days

Sum --- 1375 days;

One day of work is worth 72.7 grams of steel.



Note: I realize this doesn't include time and cost for trasport, tools and machinery.